Story summary
- NextDC announced it is suspending new development projects and land acquisitions after electricity-network upgrades were delayed.
- The delay, announced on 21 October 2026, will defer about A$140 million of revenue and cut the 2027 net-revenue outlook to A$475-500 million.
- NextDC will consider selling development sites as part of a reduced A$4.5-5 billion 2027 capex plan.
- Shares fell 41.7%, wiping about A$3 billion in value; analysts cite community opposition and Jemena’s power-supply suspension.