Snowy 2.0 Costs May Rise to $25 Billion

By Drooid · · How we work

23 5 Full Breakdown

1 of 1

Story summary
  • Snowy Hydro announced Snowy 2.0 pumped-hydro costs could rise to $25 billion.
  • The project set a $22.2 billion target cost with an allowance up to $25 billion.
  • Minister Chris Bowen and Minister Katy Gallagher said construction-sector pressure and geological challenges drove the cost growth.
  • Commissioning has been pushed back to the end of 2029.
  • CEO Dennis Barnes noted only 22 test cores were drilled for the 16-km tunnel, indicating design immaturity.