Karnataka to approve Pink Line elevated stretch in five days

By Drooid · · How we work

1 1 Full Breakdown

1 of 2

Story summary
  • Karnataka development minister Krishna Byre Gowda announced the Pink Line’s elevated section will be approved within five days.
  • Trial runs on the 19.75-km K.R. Puram–Central Silk Board Blue Line stretch will start by the end of October.
  • Construction of that Blue Line segment is 87 % complete and station entry-exit works are 88 % finished.
  • Delays resulted from a year-long court stay on tree-felling and six-to-eight-month utility relocation setbacks.