Finland orders Tuike to suspend data-center environmental work
By Drooid · · How we work
1 of 1
Story summary
- Finland’s Licensing and Supervision Authority ordered Tuike Finland to suspend environmentally significant preparatory work at Muhos and Kajaani data-center sites.
- The regulator said the work began before required environmental impact assessments were completed.
- Approximately 250,000 trees were cleared at the Muhos site during the preparatory work.
- A Finnish platform has proposed a data-center fee and tighter grid-access rules, citing the Irish model.