Back to story perspectives

Full Breakdown

Finnish Police Open Criminal Probe into Google Data-Centre Construction

By Drooid · · How we work

In this breakdown

01

Police Investigation Launch

Finnish police have opened a criminal investigation into possible breaches of the Water Act at the construction site of a planned Google data centre near Muhos. Detectives said the inquiry will examine water-management practices and could result in a corporate fine. The investigation will continue into 2027, with an update slated for December.

02

Background & Context

Alphabet’s Google announced a €13 billion AI infrastructure plan for Finland in September 2026, its largest investment in Europe. The country’s cool climate, low-carbon electricity and government support have made it a hub for data-centre projects. Prime Minister Petteri Orpo presented the deal as an economic boost, downplaying concerns about energy strain.

Visual evidence

In the northern Finnish town of Muhos, the forest has already been cut down on land acquired by Google, with excavators now clearing the ground and rumbling trucks shuttling back and forth to the construction area located next to major power lines
In the northern Finnish town of Muhos, the forest has already been cut down on land acquired by Google, with excavators now clearing the ground and rumbling trucks shuttling back and forth to the construction area located next to major power linesPhoto: theguardian
An aerial view of the site where Google’s datacentre is set to be built in Muhos
An aerial view of the site where Google’s datacentre is set to be built in MuhosPhoto: theguardian
Google’s clearcut area of about 200 hectares (500 acres) in Otanmäki, Finland
Google’s clearcut area of about 200 hectares (500 acres) in Otanmäki, FinlandPhoto: theguardian

03

Data & Statistics

  • The cleared area at Muhos covers roughly 330 ha (815 acres).
  • Campaigners estimate 250,000 trees were felled at Muhos and 150,000 at a second site in Otanmäki, about 100 km away.
  • Grid operator Fingrid projects that AI data centres could increase Finland’s electricity consumption by up to 40 percent if all approved connections proceed.
  • The Supervisory Agency (LVV) ordered Google to halt preparatory work on 6 October 2026 and to submit an improved drainage plan later this month.

04

Official Statements & Responses

  • Detective Superintendent Kari Pakanen said the probe will assess whether Google’s operations breached the Water Act and caused environmental damage.
  • Google spokesperson affirmed cooperation with investigators and emphasized compliance.
  • LVV spokesperson warned that failure to meet the deadline could trigger enforcement actions, including a fine.
  • Prime Minister Petteri Orpo reiterated that the investment would deliver lasting economic benefits.
  • Finnish Green MP Oras Tynkkynen condemned the clear-cutting as “unforgivable” and urged respect for Finnish legislation.

05

Criticism & Opposition

Environmental activists and local residents decried the scale of forest removal, arguing it distracts from broader biodiversity loss caused by Finnish forestry. Over 93,000 people have signed a petition calling for stricter regulation of data-centre projects and compensation for environmental damage. Critics say rapid approval of large-scale infrastructure threatens Finland’s natural heritage.

06

On-the-Ground Reports

Video and photos from local observers show extensive clear-cut areas and drainage trenches at Muhos. Residents said Google initially delayed responding to inquiries after the clear-cutting became public, heightening public anger. Campaigners highlighted the loss of hundreds of thousands of trees and the visual impact on the rural landscape.

07

Conflicting Reports & Gaps

  • Date of Investigation Launch: Some outlets list the police action as starting on 29 October 2026, while other records treat that date as scheduled, indicating a reporting discrepancy.
  • Tree-Felling Figures: Only The Guardian provides specific counts (250,000 at Muhos, 150,000 at Otanmäki); other sources mention the scale without quantitative detail.

08

Verbatim Quotes

  • “We are investigating whether the company’s operations have breached the Water Act and resulted in environmental damage,” — Detective Superintendent Kari Pakanen

09

What’s Next

The police investigation will run into 2027, with a formal update expected in December. Tuike Finland must submit a revised drainage and water-management plan later this month or face possible enforcement measures, including fines. The LVV’s permit review will determine whether construction can resume at the affected sites.